How to lay a roofing membrane

Steps from the Himalayan Roof membrane laying instructions. The instructions give basic recommendations and do not cover every roof solution. Installation must comply with the building documentation, regulations and good roofing practice.

Before you start

  • The membrane must not serve as temporary roofing. Lay it together with the main roofing.
  • Do not lay it on wet or freshly impregnated roof elements. Battens and counter battens must be properly impregnated.
  • Do not drag the strips over the structure, as they are easily damaged.
  • Protect the membrane from glowing swarf from cutting and from cigarette embers. Smoking is not allowed during laying.

The membrane can be stretched over the roof structure or laid on board sheathing. It can also be fitted directly onto the thermal insulation between the beams. Over a non-habitable attic, where the insulation lies on the ceiling, it is fitted in the same way.

Where the thermal insulation touches the sheathing boards, the boards should not be wider than 11 cm and must not touch each other along their full length. Wider boards require a wider gap. The wool must then be dry.

Laying the strips

  1. Start at the bottom of the roof. The strips run horizontally, parallel to the eaves, with an overlap.
  2. Lay the membrane with the printing facing up.
  3. The bottom edge should overlap the eaves flashing.
  4. The membrane is held by a well-pressed counter batten. If necessary, pre-fix it to the rafters with wide-head nails or staples, directly under the counter batten.
  5. The instructions recommend tape at fixing points. Use PE tape under counter battens.
  6. Overlap joints should be bonded, and sealed at the counter battens. Use W1 and N2 tapes for bonding.

Installation without counter battens can only be carried out at your own risk. Too many staples or nails in the sheathing can damage the membrane.

Overlaps by pitch

Roof slope pitchOverlap
36–90°10 cm
25–35°15 cm
below 25°at least 20 cm

The overlap width is usually marked by the hatching on the membrane.

Ridge and corners

The last strip is laid over the ridge with an overlap of at least 15 cm, so that the ridge itself is covered twice. At the corners, strips from adjacent planes also overlap each other.

On a ventilated roof, leave a ventilation gap under the membrane, make inlet openings at the eaves and leave the ridge open. More in the guide to roof ventilation.

Eaves

At the eaves, the membrane is bonded with N2 double-sided tape. The edge should lie on the eaves flashing or on the drip edge under the gutter and be covered by the main roofing.

Roof openings

This applies to vents, aerials, chimneys, windows and hatches.

  1. Cut the opening as closely fitted and as small as possible.
  2. Above the penetration, make a drainage channel.
  3. At walls and similar elements, overlap joints must carry water away on the outer side of the membrane.
  4. Bond the membrane with N2 double-sided tape, so that the parts turned upwards form a band 10–15 cm high.
  5. Finally, seal the cuts at the corners and any splits. For greater tightness, tape around the element with W1 tape.

This method applies to roof vents and soil vent terminals. Flue chimneys are connected to the membrane according to the applicable fire safety regulations.

Valley

Before laying the main horizontal strips, fix an additional strip of membrane along the valley. The strips from the adjacent slopes run onto it, with an overlap of at least 15 cm.

UV radiation

The sun damages the membrane, so fix the main roofing as soon as possible after laying it. It is best to lay both layers at the same time.

From the attic side the membrane must be covered, for example with thermal insulation with a vapour barrier, or the windows must be covered. You have at most 3 months from laying for this, and at the eaves at most 2 months. In a non-habitable attic that still receives daylight, cover the membrane with thermal insulation or cover the window or hatch.

Vapour barrier and consumption

It is recommended to install a vapour barrier film together with the membrane. Such an arrangement prevents moisture from collecting in the thermal insulation and roof structure.

You always use more membrane than the roof area: by 20–200%. It depends on how complicated the roof is and how many elements pass through the slope. You can work out the approximate number of rolls in the calculator.